Understanding the building stages is very important. Having a good relationship with your builder is very key and strategic to the timely completion and success of your building plan. Keep yourself informed and understand the timeframes.
You are now ready for the first drawdown. Drawdowns will be aligned to the Quantity Surveyor’s Report.
Construction process
Substructure: excavation and earthworks; reinforced concrete pad, strip, and ground beam foundations; foundation blockwork and ground floor slab.
Frame and upper floors: reinforced concrete columns, beams, suspended floor slab and staircase.
Walls: hollow core blockwork; reinforced concrete lintels and ring beam.
Roof: standing seam roof covering on metal framed construction.
Windows and doors
Services: plumbing and electrical, smoke detector(s) installations.
Finishes
Fittings and fixtures: high and low-level kitchen cupboards; vanity counters; bedroom cupboards; closets and handrails.
External works: reinforced concrete apron paving; surface water drains; septic tank and soakaway.
Preliminaries: mobilization; site supervision; insurances.